Below are the projected onsite construction activities for the next two weeks on Brentwood Bound.
Flood Mitigation Phase 1
- L. Keeley landscape maintenance activities
Flood Mitigation Phase 2
- L. Keeley landscape maintenance activities
GRG Connector Part A
- Ideal Landscaping landscape maintenance activities
Destination Playground
- Plocher installation of poured play surface for the Family Play Area
- Plocher Overlook framing and decking
- Plocher construction of seat walls
- Plocher installation of the North Play Area Structure
- Plocher Water Play runnel construction
- Plocher concrete curbing and sidewalks
- Plocher site electrical rough-in