[ARCHIVED] Brentwood Bound Construction Update - May 25, 2023

BB Construction Update

On-site construction work details anticipated in the next two weeks on the Brentwood Bound projects:

Flood Mitigation Phase 1

  • Landscaping and maintenance activities
  • Remaining punchlist work and closeout 

Flood Mitigation Phase 2

  • Finish grading
  • Connection of multi-use path to Manchester Road
  • Installation of soil amendments, seed, and erosion control fabric
  • Landscaping plantings
  • Substantial completion walkthrough
  • Punchlist and closeout activities

Deer Creek Greenway Connector Part A

  • Final cleaning and site restoration
  • Punchlist and closeout activities
  • Landscape maintenance

Destination Playground

  • Retaining wall installation
  • Structural steel fabrication
  • Heavy timber delivery and framing

MoDOT Manchester Road Improvements

  • Flatwork installation(s)
  • Ornamental lighting installation
  • Signage and fencing installation
  • Mainline paving and striping
  • Landscape plantings and sod