[ARCHIVED] MSD Project Clear Update – December 1, 2022

MSD Project Clear Update

Work anticipated in the next three weeks on Metropolitan St. Louis Sewer District’s Project Clear in Brentwood:

Deer Creek Sanitary Tunnel - Manchester and Breckenridge Industrial Site – The contractor will resume work at the site on December 1. The work will consist of removing the existing 54-inch sewer line from within the newly constructed diversion structure, installing the new slide gate and actuator at the diversion structure, and performing the start-up and testing of the gate. The contractor anticipates that this work will be completed in December. 

 