News Flash Home
The original item was published from 12/15/2022 9:38:00 AM to 12/22/2022 8:37:27 AM.

News Flash

Home

Posted on: July 2, 2020

[ARCHIVED] MSD Project Clear Update – December 15, 2022

MSD Project Clear Update

Work anticipated in the next three weeks on Metropolitan St. Louis Sewer District’s Project Clear in Brentwood:

Deer Creek Sanitary Tunnel - Manchester and Breckenridge Industrial Site – The contractor has removed the existing 54-inch sewer line from within the newly constructed diversion structure and installed the new slide gate and actuator at the diversion structure. This week the contractor performed the start-up and testing of the gate. The contractor will be installing level-sensing instruments in the structure later this week and placing the pre-cast concrete plank cover on the structure next week. This will conclude the physical work at the site, with the exception of some minor seeding work that will occur next spring. 

Facebook Twitter Email

Other News in Home