[ARCHIVED] MSD Project Clear Update – June 9, 2022

MSD Project Clear Update

Work anticipated in the next three weeks on Metropolitan St. Louis Sewer District’s Project Clear in Brentwood:

  • Deer Creek Sanitary Tunnel - Manchester and Breckenridge Industrial Site – The contractor will continue to install the electrical and control equipment on the elevated Diversion Structure platform. There will then be another pause in the work until later in the summer when the actuator for the control gate will arrive and be installed.  